Why Clause 6 Is a Hotspot for Nonconformities
If you audit ISO 45001 regularly, you already know that Clause 6 generates more nonconformities than almost any other part of the standard. Planning is where the OH&S management system either stands on solid ground or starts to wobble. Get the hazard identification wrong, and the risk assessment is compromised. Set vague objectives, and the entire performance measurement framework falls apart. Miss a legal requirement in the register, and you are looking at a potential major nonconformity before the audit has even warmed up.
On this page
This article walks through the most common nonconformities auditors find in Clause 6 of ISO 45001, clause by clause. Whether you are preparing for an internal audit, conducting a surveillance audit, or getting ready for a certification visit, understanding where organisations consistently fall short will sharpen your audit approach and help you ask the right questions.
For context, Clause 6 covers general planning requirements under 6.1.1, hazard identification under 6.1.2.1, OH&S risk assessment under 6.1.2.2, opportunity assessment under 6.1.2.3, legal and other requirements under 6.1.3, planning action under 6.1.4, OH&S objectives under 6.2.1, and planning to achieve those objectives under 6.2.2. That is a lot of territory, and each subclause has its own common failure modes.
Clause 6.1.1: Risks and Opportunities Not Properly Determined
The general planning clause asks organisations to consider risks and opportunities beyond just OH&S hazards. This includes risks and opportunities related to the OH&S management system itself, such as the risk that the system is not integrated into operations, or the opportunity to improve worker participation. Many organisations confuse this with the hazard and risk assessment in 6.1.2, and the two are not the same thing.
What auditors commonly find
The most frequent gap here is that the organisation has simply not documented any consideration of risks and opportunities at the system level. There is a hazard register, there are risk assessments, but there is nothing that addresses systemic risks such as high staff turnover in safety critical roles, or opportunities such as adopting new control technologies. Auditors will ask to see evidence that these have been considered, and often find blank stares in response.
Another common finding is that the outputs of the 6.1.1 assessment are not carried through into planning. The standard requires that actions addressing risks and opportunities are integrated into the OH&S management system processes and that their effectiveness is evaluated. If the organisation has produced a document listing system level risks but has taken no action on them, that is a nonconformity waiting to be written.
You can read more about what this clause specifically requires in our article on risks and opportunities in ISO 45001: Clause 6.1.1 explained.
Exemplar Global Certified Training ProviderRTP No. 310970Clause 6.1.2.1: Hazard Identification That Is Incomplete or Out of Date
Hazard identification is the foundation of the entire OH&S risk management process. If the hazard identification is incomplete, everything built on top of it is unreliable. This is one of the most consistently problematic areas in ISO 45001 audits, across industries and organisation sizes.
The hazard register that never gets updated
The single most common nonconformity under 6.1.2.1 is a hazard register that has not been maintained. Organisations often do a thorough job at the time of initial certification, produce a comprehensive hazard identification document, and then leave it untouched for years. The standard requires that hazard identification is an ongoing process, not a one time exercise.
Auditors look for evidence that hazard identification happens when changes occur, when incidents happen, when new equipment is introduced, when work arrangements change, and at planned intervals. If the register was last updated two years ago and the organisation has introduced new chemicals, changed shift patterns, or taken on new work, that is a nonconformity.
Hazards identified without worker input
The standard specifically requires that hazard identification takes into account how work is actually organised, including social factors, leadership, and the work culture. It also requires consideration of past incidents and near misses. Auditors regularly find that the hazard identification process is conducted entirely by management or the HSEQ team, with no meaningful input from the workers who actually do the work.
Ask a shop floor worker whether they were involved in identifying hazards for their area. If the answer is no, or if they look confused by the question, you have found a gap. The hazard register may be technically complete, but the process used to create it does not meet the standard.
Our article on auditing hazard identification covers the specific questions to ask and evidence to look for when auditing this process.
Clause 6.1.2.2: OH&S Risk Assessment Weaknesses
Once hazards are identified, the organisation must assess the OH&S risks associated with those hazards. This is where many organisations produce something that looks like a risk assessment but does not actually meet the requirements of the standard.
Risk ratings that are not credible
The most common issue auditors find is a risk matrix where every hazard ends up rated as low or medium after controls are applied, regardless of the actual severity of the hazard. This is the risk assessment equivalent of grade inflation. If a confined space entry task with inadequate permit controls is rated as a low risk, the risk assessment has not been done honestly.
Auditors should probe the methodology. Ask how the organisation determined that the residual risk is acceptable. Ask what evidence supports the control effectiveness rating. If the answer is essentially that someone in the office made a judgement call with no documented basis, that is a finding.
No methodology documented
The standard requires that the risk assessment methodology is defined. Many organisations have a risk matrix but no documented process explaining how to use it, what the rating criteria mean, or who is responsible for conducting assessments. Without a documented methodology, results cannot be consistent or repeatable, which is exactly what the standard is trying to achieve.
Another gap is the failure to reassess risks after controls are implemented. Organisations often assess the initial risk, list some controls, and stop there. The standard expects that residual risk is also assessed, and that the adequacy of controls is evaluated against the residual risk level.
Clause 6.1.2.3: OH&S Opportunities Overlooked Entirely
This is probably the most consistently neglected subclause in all of Clause 6. The standard requires that the organisation assess OH&S opportunities alongside OH&S risks. Opportunities include things like adapting work to improve worker health, eliminating hazards through better design, and improving OH&S performance through better worker engagement.
In practice, most organisations either have not heard of this requirement or have produced a token document that lists generic opportunities with no real analysis behind them. Auditors frequently find that the opportunity assessment has been copied from a template and bears no relationship to the actual organisation or its operations.
The fix is not complicated. The opportunity assessment should be specific to the organisation, tied to the hazards and risks already identified, and linked to actions. If the hazard identification has identified manual handling as a significant hazard, the opportunity assessment should ask whether there is an opportunity to eliminate or reduce that hazard through engineering controls, job redesign, or procurement of different equipment.
For a detailed look at what auditors check in this area, see our article on how auditors evaluate OH&S opportunity assessment in Clause 6.1.2.3.
Clause 6.1.3: Legal Register Problems Are Extremely Common
The legal and other requirements clause generates a high volume of nonconformities, and many of them are major. The standard requires that the organisation determines and has access to the legal requirements and other requirements applicable to its OH&S hazards, and that it keeps this information up to date.
The register that has not been reviewed
The most common finding is a legal register that has not been updated since certification. Work health and safety legislation changes regularly in Australia, and an organisation that certified three years ago and has never reviewed its legal register is almost certainly missing current obligations. Auditors ask for evidence of the last review date and what process is used to identify changes in legislation.
In one audit of a construction company in Queensland, the legal register referenced regulations that had been superseded more than two years earlier. The organisation had no process for monitoring legislative changes, and no one had been assigned responsibility for keeping the register current. That was a clear major nonconformity.
Requirements not evaluated for compliance
Having a legal register is not enough. The standard also requires that the organisation evaluates how these requirements apply to its hazards and risks, and that this information is communicated to workers. Auditors frequently find that the register exists as a list of legislation but there is no evidence that the organisation has assessed whether it is actually complying with each requirement.
Ask the organisation to walk you through how they evaluate compliance with a specific regulation. If they cannot demonstrate that process, or if the evaluation has never been done, that is a nonconformity against 6.1.3.
Clause 6.1.4: Actions Not Planned Properly
Clause 6.1.4 requires that the organisation plans actions to address the risks, opportunities, and legal requirements identified in the preceding subclauses. It also requires that the organisation considers how to integrate these actions into its OH&S management system processes, and how to evaluate the effectiveness of those actions.
The most common nonconformity here is that actions exist in isolation. The hazard register might identify a risk, and there might be a corrective action somewhere in a spreadsheet, but there is no clear link between the two. Auditors look for a traceable connection from identified risk to planned action to implementation to effectiveness evaluation.
Another frequent gap is that actions are planned but never evaluated for effectiveness. The organisation implements a control, ticks the box, and moves on. There is no evidence that anyone checked whether the control actually reduced the risk. This is a systemic failure that often points to broader issues with continual improvement.
Our article on planning action in ISO 45001: making sense of Clause 6.1.4 goes into the specific requirements and common audit questions in detail.
Clause 6.2.1: OH&S Objectives That Do Not Meet the Requirements
The standard sets out specific criteria for OH&S objectives. They must be consistent with the OH&S policy, measurable where practicable, take into account applicable requirements, be relevant to the enhancement of OH&S performance, and be monitored, communicated, and updated as appropriate. Many organisations fall short on several of these criteria at once.
Objectives that are not measurable
The most common finding under 6.2.1 is objectives that are stated in vague terms with no measurable target. An objective that says “improve safety culture” or “reduce incidents” without a specific target, baseline, or timeframe does not meet the standard. Auditors ask how the organisation would know whether the objective has been achieved. If the answer is uncertain, the objective is not measurable.
Objectives not linked to the OH&S policy or significant risks
Objectives should flow logically from the OH&S policy and from the significant risks and opportunities identified in the planning process. Auditors regularly find objectives that appear to have been set in isolation, with no visible connection to the hazard and risk assessment or the policy commitments. This suggests the planning process is not integrated, which is a systemic concern.
In one audit of a manufacturing facility, the OH&S objectives for the year included reducing paper use in the safety office and improving the look of the safety noticeboard. Neither objective had any meaningful connection to the significant OH&S risks identified for the site. The auditor raised a nonconformity for failure to set objectives that were relevant to the enhancement of OH&S performance.
Clause 6.2.2: Planning to Achieve Objectives Is Often Superficial
Even when objectives are well written, the planning to achieve them is often inadequate. Clause 6.2.2 requires that the organisation determines what will be done, what resources are required, who will be responsible, when it will be completed, and how results will be evaluated. This is a five part requirement, and many organisations address only one or two parts.
The most common gap is missing information about resources and evaluation. The organisation has a table listing objectives, responsible persons, and target dates, but there is no indication of what budget or other resources have been allocated, and no method for evaluating whether the actions taken have actually achieved the objective.
Auditors should request the objective planning documentation and check each of the five elements systematically. Ask the responsible person to explain how they will know whether the objective has been achieved. If they cannot answer clearly, the planning is incomplete.
Systemic Patterns to Watch For
When you see multiple nonconformities across Clause 6, it is worth stepping back and considering whether there is a systemic cause. Common systemic patterns include:
- Planning documents that were created at the time of certification and have never been reviewed or updated.
- Responsibilities for planning activities that have not been clearly assigned, so no one owns the process.
- A disconnect between the people who write the planning documents and the people who actually do the work.
- No process for reviewing the planning outputs when changes occur, such as new processes, new equipment, or new legislation.
- Management review that does not actually review the Clause 6 outputs, so problems accumulate undetected.
When you identify a systemic pattern, document it clearly in your findings. A systemic finding is more valuable than a collection of individual findings because it points to a root cause that, if addressed, will fix multiple problems at once.
Exemplar Global Certified Training ProviderRTP No. 310970Practical Audit Tips for Clause 6
Here are some practical approaches that experienced auditors use when auditing Clause 6 of ISO 45001:
- Start with the hazard register and trace a sample of hazards through to the risk assessment, then to planned actions, then to the objectives. This vertical trace will reveal gaps in the chain quickly.
- Ask workers whether they were involved in hazard identification and whether they know the OH&S objectives for their area. Worker awareness is a useful indicator of how well the planning process is embedded.
- Check the date on every planning document. If the legal register, hazard register, and risk assessment all have the same date and it was three years ago, that tells you something important about how the organisation maintains its planning outputs.
- Request evidence of the last management review and check whether Clause 6 outputs were reviewed. If management review does not cover the planning outputs, the system is not being monitored effectively.
- When you find a gap in one subclause, follow the thread. A weak hazard identification process will almost certainly produce a weak risk assessment, which will produce inadequate actions and irrelevant objectives. Document the chain.
Building Audit Competence in OH&S Planning
Auditing Clause 6 of ISO 45001 effectively requires more than a checklist. You need to understand how the planning requirements connect to each other and to the rest of the standard, and you need the interviewing skills to probe beyond surface level answers.
If you want to develop that competence, Audit Workshop offers ISO 45001 Internal Auditor and Lead Auditor training that covers Clause 6 in depth, including practical exercises based on real audit scenarios. The training is delivered by Dilawar Laghari, a certified lead auditor with over 14 years of compliance experience and more than 500 external ISO certification audits. You will learn how to identify the nonconformities described in this article, how to write them up clearly, and how to trace systemic issues back to their root causes. Explore the ISO 45001 Lead Auditor course options to find the right level for your current experience.